T-Bar system is ceiling system which realized aesthetical sense and practicality. It is very simple to work and in whole span of installation it is possible to check. It facilitates repair and checking of wiring or pipinjg etc. It is a system suitable to all the internal parts of building architecture such as general offices and shopping mall etc. T-Bar with width of 25mm creates solumn and classic ceiling.

General matters for STEEL T-BAR 25mm


(1) Definition of terms

  • ① System: Steel T-bar system
  • ② Method; Lay-in (A type whereby ceiling finishing panel is placed on ceiling frame)

(2) Transportation and handling

  • ① Transportation: Transport after recording type, name, dimension and manufacturing date etc. on the label and then packing.
  • ② Handling: Handle it according to instruction of manufacturer and requirement of the user.

Steel-T-Bar 25 mm product

(1) Material

  • KSD 3506 (melt galvanized steel plate)
    KSD 3520 (painted melt galvanized steel plate)
    KSD 3609 (steel material support for construction?supplementary materials : T-bar etc.)
  • ② Color : white (standard color) and order color

(2) Dimension

  • ① STEEL MAIN T-BAR 25 mm x 38mm x 0.4T
  • (for general purpose L=3658, for Ziebart L=3600)
  • ② STEEL MAIN T-BAR 25 mm x 38mm x 0.4T
  • (for general purpose L=610, for Ziebart L=600)
  • ③ HANGER BOLT : ψ9mm
  • ④ HANGER & PIN : 105mm X 20mm X 2.0T
  • ⑤ CARRYING CHANNEL : 38mm X 12mm X 1.2T
  • ⑥ C/C JOINT : 100mm X 35mm X 10mm X 1.0T
  • ⑦ C/T CLIP (for Steel T-bar)
  • ⑧ MINOR CHANNEL : 19mm X 10mm X 1.2T
  • ⑨ M/C CLIP : 38mm X 23mm X 14mm X 1.2T
  • ⑩ HANGER NUT : ψ9mm
  • ⑪ MOLDING (for Steel T-bar)
  • ⑫ ANGLE MOLDING : 22mm X 32mm X 0.5T
  • ⑬ DOUBLE MOLDING : 15mm X 10mm X 15mm X 24mm X 0.5T

Special feature for Steel T-bar


  • * Working is fast and simple.
  • * Any ceiling plate can play role for checking hole.
  • * Width of bar is modern thus it has solumness.
  • * Removes sense of monotony by presenting cross stripes ceiling.

(1) Setting centerline of building: After accurate measurement of ceiling surface set up centerline after checking other work schedule such as lightline and position of diffuser etc.

    (2) Strong anchor work

    • ① At the time of strong anchor work when centerline is set up mark part for fixing strong anchor (Ф9mm) at slab surface and punch hole with drill and fix it.
    • ② At the time of work for cash iron insert (Ф9 mm) install it at form according to drawing.
    • ③ Caution: Pay attention to intervals between anchor and insert and right angle.
    • ④ It is ideal to make interval for installation as @900∼ 1,200 mm for strong anchor or insert in consideration of direction of installation of carrying channel.

    (3) Molding line level check

    • ① Use of water level or level
    • a. Confirming position by means of drawing (confirming height of ceiling)
    • b. Confirming the position by water level and ink pot string marking between positions.
    • ② Caution: At the time of using water check make sure to check level after checking any presence of air bubble in hose and breaking of hose.

    (4) Attachment of wall molding (using after painting angle or sea gull molding)

    • ① Attach molding along the India ink line and fix wall molding by using 1" concrete nail.
      (interval 500∼ 1,000 mm)
    • ② Be careful not to slacken the height and interval between moldings.
    • ③ In connection with facilities such as curtain box it shall be attached according to specification.

    (5) Installation of hanger bolt

    • ① Upper part of hanger bolt is fixed to strong anchor or insert and power part of bolt is fixed with hanger and nut in consideration of ceiling height at finishing.
    • ② At the place where installation duct or other obstacles are present work shall be carried out after reinforcing it according to specification.

    (6) Installation of lightline

    • Install lightline according to specification but it is required to have consultation with persons in charge of electricity and facility.

    (7) Installation of carrying channel

    • After linking hanger set and carrying channel fix it and install it with an interval of @900∼1,200 mm. The joint part of carrying channel shall be connected by using carrying joint.
    • At the time of installing carrying channel make sure to install it not to be off from wall or curtain box surface more than 30 cm.

    (8) Installation of minor channel

    • When area for works is broad reinforce and fix with supplementary channel (minor channel) installed above the carrying channel and install it with an interval of @2,000∼ 3,000 mm.

    (9) Installation of Main ST' LT-bar

    • ① Install Main ST' LT-bar sturdily by using C/T cup toward right angle direction to carrying channel according to dimension of the product and lightline.
    • ② Intervals for installation: for general T-bar interval is @610 mm and for Zierbart interval for installation is @600 mm.
    • ③ It is installed by inserting CROSS ST' LT-Bar Tip to hole of Main ST' LT-bar.
      (Interval of hole: for general use it is @152.4 mm and for Ziebart it is @150 mm.)
    • ④ At the time of installation of CROSS ST' LT-Bar hole of MAIN ST'LT-BAR shall match to hole of another MAIN ST'LT-BAR.

    (10) Installation of finishing plate (sound absorption tex/ Ziebart)

    • ① Accurately set level of installed ceiling frame by bolt and nut through using water level or level.
    • ② Place sound absorption tex or Ziebart on Main and Cross ST' LT-bar after its installation. (In case of sound absorption tex fix finishing plate with hold down clip.)
    • ③ Prohibit use of finishing plate with scratch, broken corner or dirtied.

    (11) Installation of curtain box

    • ① Manufacturing and installing products suitable to use according to specification (separate painting)
    • ② Welding work is carried out concurrently therefore install work bench to enable safety in work and working in comfortable stance.

    Loading...Please wait a moment!